Paysheet #11125

Job Created: 11/12/25
Job Number: CP25574 Job Name: LEAK REDUCTION PROJECT
Job Notes: 486 Rising hill dr rear easement stl main leak investigation crew took bar hole readings and then dug on hot spot crew dug up 2” stl main with a saddle feeding 1 1/4 stl main on the 1 1/4 crew found compression leaking crew was able to clean it up and tighten to eliminate the leak. Crew took pipe to soil reading re coated main and did backfill clean up took bar hole readings to verify 0% gas reads
SAP Workorder Number: 116661968
 
Foreman Name:Tyler
Work Dates: 11/12/25 - 11/12/25
Item - Description Item Qty Item UOM
3013525 - T & M: Three-Person Construction Crew, Straight Time 5 HR
Extra Service Items:


THIS ORDER IS: APPROVED