Paysheet #1550

Job Created: 07/26/22
Job Number: VEC2226 Job Name: V-2418
Job Notes: Saw cut and removed sidewalk blocks on Linden Ave for open cut. Open cut and installed new 4” plastic main down the sidewalk on Linden Ave. Backfilled ditch line on Linden Ave. Tried digging up the existing 4” plastic main for tie in point on Linden Ave at Davis Ave, spent 4 hours digging and trying to find the existing main on paint marks but couldn’t find it, tried open cut stripping the grass and removing sidewalk blocks and digging holes but still can’t find the existing 4” plastic main.
SAP Workorder Number: 98784413
 
Foreman Name:Anthony Delawder
Work Dates: 07/25/22 - 07/25/22
Item - Description Item Qty Item UOM
3013603 - Combo Dig/Backfill: Saw Cut Hard Surface Prior to Removal less than or equal to 6" 30 FT
3013673 - Combo Dig/Backfill: Remove sidewalk (including disposal) 800 SF
3013907 - Install 3" & 4" - >2000' by trench 120 FT
3013407 - Combo Dig/Backfill: Provide & place sand fill 22.67 TON
3013408 - Combo Dig/Backfill: Provide & place gravel fill 65.35 TON
3013525 - T & M: Three-Person Construction Crew, Straight Time 4 HR
Extra Service Items:


THIS ORDER IS: APPROVED

CLICK HERE TO SEE ANY AVAILABLE ATTACHMENTS