Paysheet #4719

Job Created: 08/22/23
Job Number: CP23224 Job Name: 2023 CP MODERNIZATION
Job Notes: Saw cut and removed concrete on Joyce Ann Dr. Potholed utilities in bore path on Joyce Ann Dr. Bored in 700’ of 2” HDPE pipe on Joyce Ann Dr.
SAP Workorder Number: 100116215 / V-X -1064
 
Foreman Name:Anthony Delawder
Work Dates: 08/21/23 - 08/21/23
Item - Description Item Qty Item UOM
3013603 - Combo Dig/Backfill: Saw Cut Hard Surface Prior to Removal less than or equal to 6" 30 FT
3013673 - Combo Dig/Backfill: Remove sidewalk (including disposal) 44 SF
3013418 - Combo Dig/Backfill: Spot Holes - hard surface (to ensure separation of facilities during boring activities) 4 EA
3013416 - Combo Dig/Backfill: Spot Holes - soft surface (to ensure separation of facilities during boring activities) 1 EA
3013269 - MAIN: INSTALL 2" - >2000' BY BORE 700 p/ft
Extra Service Items:


THIS ORDER IS: APPROVED