Job Created: 10/04/23
Job Number: CP23224 Job Name: 2023 CP MODERNIZATION
Job Notes: Trenched in 2” HDPE pipe and wire on N. Main St. Bored in 2” HDPE pipe and wire on N. Main St. Potholed utilities in bore paths on Cedarlawn Drive.
SAP Workorder Number: 100116215 / V-X -1064
 
Foreman Name:Anthony Delawder
Work Dates: 10/03/23 - 10/03/23
Item - Description Item Qty Item UOM
3013603 - Combo Dig/Backfill: Saw Cut Hard Surface Prior to Removal less than or equal to 6" 8 FT
3013412 - Combo Dig/Backfill: Remove roadway (parking lot, street, driveway) (including disposal) 4 SF
3013673 - Combo Dig/Backfill: Remove sidewalk (including disposal) 25 SF
3013418 - Combo Dig/Backfill: Spot Holes - hard surface (to ensure separation of facilities during boring activities) 1 EA
3013416 - Combo Dig/Backfill: Spot Holes - soft surface (to ensure separation of facilities during boring activities) 5 EA
3013903 - Install 2" - >2000' by trench 7 FT
3013269 - MAIN: INSTALL 2" - >2000' BY BORE 500 p/ft
3013605 - Combo: Flagman 8 HR
Extra Service Items:


THIS ORDER IS: APPROVED