Paysheet #5189

Job Created: 10/19/23
Job Number: CP23224 Job Name: 2023 CP MODERNIZATION
Job Notes: Installed and built regulator setting on Philadelphia Dr. Installed protective bollards around reg. Setting. Tested main and regulator setting. Removed test and tied 2” HDPE inlet pipe to 2” HDPE MPPL main on Philadelphia Drive. Tapped 4” MPSTL main on outlet side of the regulator setting. Purged all air from regulator setting. Helped Centerpoint assemble and get regulator setting running. Greased and wrapped steel. Backfilled all holes.
SAP Workorder Number: 100116215 / V-X -1064
 
Foreman Name:Anthony Delawder
Work Dates: 10/17/23 - 10/18/23
Item - Description Item Qty Item UOM
3013605 - Combo: Flagman 20 HR
3013404 - Svc: Install Protective Post 4 EA
3013525 - T & M: Three-Person Construction Crew, Straight Time 10 HR
3013529 - T & M: Welder With Welding Rig - straight time 30 HR
3013538 - T & M: Welder Helper - straight time 30 HR
3013283 - Main: 2" plastic to plastic tie-in, with tap 1 EA
3013306 - Main: 2" steel tie-in, with tap 1 EA
3013307 - Main: 3" & 4" steel tie-in, with tap 1 EA
3013532 - Combo: Contractor-Supplied Materials (cost plus 5% markup) 792.36 EA
Extra Service Items:


THIS ORDER IS: APPROVED

CLICK HERE TO SEE ANY AVAILABLE ATTACHMENTS