Paysheet #5299

Job Created: 11/02/23
Job Number: CP23224 Job Name: 2023 CP MODERNIZATION
Job Notes: 136 Elm Hill Dr, spotted new and old main in soft surface, and water in hard surface (2’x2’), bored 40’ and trenched in 39’ of 1” HDPE, retired steel in separate hole, set new riser, meter loop, and meter, tested house line and service line, relight on appliances, backfilled and cleaned up.
SAP Workorder Number: 108161886 / V-X-1064
 
Foreman Name:John Greene
Work Dates: 11/01/23 - 11/01/23
Item - Description Item Qty Item UOM
3013258 - Svc: 76-125' long side - with main 1 EA
3013412 - Combo Dig/Backfill: Remove roadway (parking lot, street, driveway) (including disposal) 4 SF
3013416 - Combo Dig/Backfill: Spot Holes - soft surface (to ensure separation of facilities during boring activities) 2 EA
3013418 - Combo Dig/Backfill: Spot Holes - hard surface (to ensure separation of facilities during boring activities) 1 EA
3013608 - Svc: Relight Customer Appliances 1 EA
3013603 - Combo Dig/Backfill: Saw Cut Hard Surface Prior to Removal less than or equal to 6" 8 FT
3013445 - RETIRE STEEL SERVICE-SEPARATE HOLE =<2" 1 EA
Extra Service Items:


THIS ORDER IS: APPROVED