Paysheet #5802

Job Created: 01/22/24
Job Number: CP2410 Job Name: V-X-3874 PKG 80 - 103094629
Job Notes: V-X-3874 - T&M Request. Mobilize equipment to project site , Clear brush small trees, Level , prep area for access. Furnish and place timber mats (8) , off load pipe and pothole existing utilities.
SAP Workorder Number: 103094629 / V-X-3874 2023
 
Foreman Name:Anthony Delawder
Work Dates: 01/02/24 - 01/05/24
Item - Description Item Qty Item UOM
3013586 - T & M: Lowbow Tractor-Trailer 19 HR
3013525 - T & M: Three-Person Construction Crew, Straight Time 29.5 HR
3013546 - T & M: Laborer - straight time 9 HR
3013560 - T & M: Excavator >50,000 lbs 51 HR
3013693 - T & M: 850 25.5 HR
3013542 - T & M: Operator - straight time 16 HR
3013593 - T & M: Vacuum Excavator, Truck / Trailer 16 HR
3013532 - Combo: Contractor-Supplied Materials (cost plus 5% markup) 250 EA
3013532 - Combo: Contractor-Supplied Materials (cost plus 5% markup) 69.78 EA
3013532 - Combo: Contractor-Supplied Materials (cost plus 5% markup) 5896.64 EA
3013532 - Combo: Contractor-Supplied Materials (cost plus 5% markup) 1056 EA
3013544 - T & M: Truck Driver - straight time 48.5 HR
Extra Service Items:


THIS ORDER IS: APPROVED