Job Notes: Setup traffic control and flaggers on W. 2nd St and June Dr. Saw cut and hammered out asphalt in the road. Dug up existing 4” steel medium pressure main for medium pressure main retirement. Dug up existing 3” medium pressure steel main at 878 W. 2nd St. Helped welder install 3” short stop and two 2” short stops on 3” steel main. Tested fittings and tapped out. Setup equipment to stopple off 3” and 4” steel mains. Stoppled off mains, cut out sections of steel main and welded on steel dead end caps on live sides. Removed all stopple equipment and plate off holes for the night. Removed traffic control and flaggers.
SAP Workorder Number: 103771118 / V-X-6017
 
Foreman Name:Anthony Delawder
Work Dates: 12/26/24 - 12/26/24
Item - Description Item Qty Item UOM
3013314 - Main Ret: 2"-3"-4" steel main retirement separate hole-stopper 2 EA
3013603 - Combo Dig/Backfill: Saw Cut Hard Surface Prior to Removal less than or equal to 6" 36 FT
3013412 - Combo Dig/Backfill: Remove roadway (parking lot, street, driveway) (including disposal) 128 SF
3013605 - Combo: Flagman 20 HR
3013582 - T & M: Pick-up truck 8 HR
3013532 - Combo: Contractor-Supplied Materials (cost plus 5% markup) 8.96 EA
Extra Service Items:


THIS ORDER IS: APPROVED